Dear Neighbors,
Here is the latest on the building project as of our PROGRESS MEETING OF 11/11/2026 -
THE PROJECT IS MOVING ALONG WELL.
NEW PROJECT SCHEDULE TENTATIVELY APPROVED WITH NEW COMPLETION DATE OF MARCH 19TH. 2027.
HERE IS WHERE THINGS STAND:
CRITICAL PATH ITEMS: TEMP WATERPROOFING TO ALLOW OTHER PRIMES TO CONTINUE - COMPLETED ORDER/INSTALL FLOOR TRENCH DRAINS - COMPLETED MASONRY BLOCK -(submittals/work) -SUBMITTALS COMPLETED, WORK ONGOING. FRAMING CARPENTRY- Submittals and work) -90% COMPLETE. ROOFING SYSTEM (TO WATERTIGHT THE BUILDING) - 95% COMPLETED WINDOWS, RFP DOORS TO BE RELEASED AND BEGIN FABRICATION - COMPLETED WINDOWS INSTALLATION - COMPLETED REAR OF BUILDING FRAMING AND CARPENTRY WORK - 95% COMPLETED BOILER RM CONSTRUCTION -95% COMPLETED ELECTRICAL RM CONSTRUCTION - 95% COMPLETED BATHROOM AND KITCHEN WORK CARPENTRY CONSTRUCTION WORK - NOT STARTED NYSEG TRANSFORMER DELIVERY AND MAIN SWITCHGEAR CONNECTION WORK - ONGOING ELECTRICAL MAIN DIST. PANEL WORK - HVAC BOILER AND PIPING - ..............ONGOING.
Nurzia will continue with Site Work prep for aprons, curbing and sidewalks. Nurzia to begin forming and placing concrete for aprons and curbs. Tri State started EFIS system on kitchen addition. Mason Sub to continue with brick veneer and stone installation on north facade.
ACS MECH. - HVAC Pipe fitters installing Hydronic Heating pipe for Kitchen and office Addition will return on Monday 11/16/2026. Ocean Breeze Sheet Metal Sub is on site installing fresh air ductwork and boiler makeup air duct on first floor apparatus bay.
The need to keep the building in service as we work is challenging, but we are attacking the project on multiple fronts and making good progress.
Happily, it's beginning to look more like a building and less like a construction site. As we move forward, we appreciate your patience.